Project Information

Project Description

The project consists of 2 four-storey residential blocks, 1 single-storey service building and 1 single-storey elderly centre. By applying the Modular Integrated Construction (MiC) method, the residential blocks offer a total of 601 units with a maximum capacity for approx. 1,000 residents at any one time. The Project provides 519 units for 1-2 persons, 80 units for 3-4 persons, and 2 accessible units or for 5-6 persons. Each residential unit contains separate areas for toilet, shower and kitchen to meet the various needs of residents.

Location

The project is located on 200 Ping Che Road, Ta Kwu Ling, New Territories. It occupies a site area of approximately 130,000 square feet.

Transportation

- Residents' bus route NR118, Pok Oi Sing Ping Village to Sheung Shui Station
- Bus route 79K, Sheung Shui to Ta Kwu Ling (Tsung Yuen Ha)
- Green minibus route 52K, Fanling Station to Ping Che

Flat Type

1-2 persons flat

154 sq. ft. (Internal Floor Area)

3-4 persons flat

228 sq. ft. (Internal Floor Area)

5-6 persons /
Accessible flat

325 sq. ft. (Internal Floor Area)

Rent

  • The monthly licence fee (including management fee and rates)
  • The licence period (i.e. lease term) is 2 years (might have an option to renew)

Non CSSA Recipient
CSSA Recipient
1-2p Flat
Monthly Rent: $1,917
3-4p Flat
Monthly Rent: $2,552
5-6p Flat /
Accessible Unit
Monthly Rent: $4,059
Refer to the Rent
Allowance of CSSA Scheme

Rent

  • The monthly licence fee (including management fee and rates)
  • The licence period (i.e. lease term) is 2 years (might have an option to renew)

Non CSSA Recipient
1-2p Flat
Monthly Rent: $1,917
3-4p Flat
Monthly Rent: $2,552
5-6p Flat /
Accessible Unit
Monthly Rent: $4,059
CSSA Recipient
Refer to the Rent
Allowance of CSSA Scheme

Project Timeline

The construction works of the project commenced in November 2022; the project completed in July 2024. Tenant intake for 601 residential units commenced in August 2024.

Commencement of construction works

November 2022
1864215_arrow_direction_right_wayfinding_icon-120x120-M

Completion of construction works

July 2024
1864215_arrow_direction_right_wayfinding_icon-120x120-M

August 2024

Third Quarter of 2024

Commencement
of
construction
works

November 2022
1864215_arrow_direction_right_wayfinding_icon

Completion of construction works

July 2024
1864215_arrow_direction_right_wayfinding_icon

Tenant intake for all residential units

August 2024